Suppose your burdened straight-time Journeyman rate is $61.52/hr ($44.00 base + $4.47 payroll taxes + $4.55 Workers’ Comp/GL + $8.50 health/pension fringe). When the GC directs Saturday overtime to recover their schedule, what is your 1.5x overtime cost?
The #1 Mistake: Multiplying $61.52 × 1.5 = $92.28/hr. Experienced GC Project Managers spot this in ten seconds and bounce the entire Change Order Request.
Why $61.52 × 1.5 Is Mathematically Wrong
- Workers’ Compensation (NCCI Rule): In nearly all US jurisdictions, Workers’ Comp premiums are audited on straight-time payroll—the 0.5x overtime premium is excluded from insurance premium calculation.
- Fixed Hourly Fringes: Health insurance and union/shop pension contributions are paid per hour worked ($8.50/hr), not 1.5x on Saturdays.
- FICA & Payroll Taxes: Social Security and Medicare (7.65%) do apply to the full 1.5x ($66.00/hr) overtime wage.
The GC-Proof Overtime Formula
When you price 1.5x overtime as ($44.00 × 1.5) + ($66.00 × 10.15% Tax) + ($44.00 × 10.35% WC/GL) + $8.50 Fringe = $85.75/hr (plus contractual O&P), no Project Manager or Owner’s Representative can dispute a single penny.
Stop Leaving 30% Labor Burden on the Jobsite Floor