Why Subcontractors Lose 30% on T&M Extra Work by Billing Base Wages Instead of True Labor Burden

By ChangeOrderPacket Estimating Team · Updated Nov 26, 2026 · 3 min read

Every week on commercial jobsites across the US, trade foremen get pulled aside by a General Contractor Superintendent with the classic promise: “Go ahead and relocate those six drops today on T&M—just send the office your hours.”

Three days later, the subcontractor prices the ticket using the Journeyman’s paycheck rate (say, $44.00/hr) plus 15% Overhead & Profit ($50.60/hr). The subcontractor thinks they made 15%. In reality, they just paid out of pocket to perform the General Contractor’s extra work.

What Employer Labor Burden Actually Includes

Base hourly pay is only what appears on the worker’s W-2 gross line. Every hour a craft worker stands on a jobsite triggers five mandatory employer-paid costs before your office lights or trucks are paid for:

Burden Component Typical US Trade Range Applies To
FICA (Social Security 6.2% + Medicare 1.45%) 7.65% All wages paid
Federal & State Unemployment (FUTA / SUTA) 1.80% – 4.20% Taxable wage base
Workers’ Compensation Insurance 5.50% (Elec) – 18.00%+ (Roofing) 1.0x Straight-Time Payroll
General Liability Payroll Allocation 1.25% – 2.50% Payroll basis
Health, Union, Pension & PTO Fringes $5.00 – $24.00 / hr Hours worked (1.0x)
Real Example: At $44.00/hr base wage + 20.50% statutory payroll/insurance burden ($9.02/hr) + $8.50/hr health/retirement fringe, your true break-even craft cost is $61.52/hr—before adding a single cent of Overhead & Profit.

Why GCs Reject “Black-Box” Shop Rates (And How to Fix It)

If you type a flat “$85/hr Electrician” on an Excel sheet with zero backup, the GC Project Manager will redline it immediately. When you attach an Itemized Labor Burden Justification Sheet showing FICA, FUTA/SUTA, Workers’ Comp class rate, and hourly fringe separately from your contractual O&P markup, the PM has audit-ready documentation for the Owner.

Stop Leaving 30% Labor Burden on the Jobsite Floor