Every week on commercial jobsites across the US, trade foremen get pulled aside by a General Contractor Superintendent with the classic promise: “Go ahead and relocate those six drops today on T&M—just send the office your hours.”
Three days later, the subcontractor prices the ticket using the Journeyman’s paycheck rate (say, $44.00/hr) plus 15% Overhead & Profit ($50.60/hr). The subcontractor thinks they made 15%. In reality, they just paid out of pocket to perform the General Contractor’s extra work.
What Employer Labor Burden Actually Includes
Base hourly pay is only what appears on the worker’s W-2 gross line. Every hour a craft worker stands on a jobsite triggers five mandatory employer-paid costs before your office lights or trucks are paid for:
| Burden Component | Typical US Trade Range | Applies To |
|---|---|---|
| FICA (Social Security 6.2% + Medicare 1.45%) | 7.65% | All wages paid |
| Federal & State Unemployment (FUTA / SUTA) | 1.80% – 4.20% | Taxable wage base |
| Workers’ Compensation Insurance | 5.50% (Elec) – 18.00%+ (Roofing) | 1.0x Straight-Time Payroll |
| General Liability Payroll Allocation | 1.25% – 2.50% | Payroll basis |
| Health, Union, Pension & PTO Fringes | $5.00 – $24.00 / hr | Hours worked (1.0x) |
Why GCs Reject “Black-Box” Shop Rates (And How to Fix It)
If you type a flat “$85/hr Electrician” on an Excel sheet with zero backup, the GC Project Manager will redline it immediately. When you attach an Itemized Labor Burden Justification Sheet showing FICA, FUTA/SUTA, Workers’ Comp class rate, and hourly fringe separately from your contractual O&P markup, the PM has audit-ready documentation for the Owner.
Stop Leaving 30% Labor Burden on the Jobsite Floor
Build your Portrait COR Proposal, Landscape Burdened T&M Audit Sheet, and Unpriced Field Ticket PDF in 90 seconds.